I visited the site of major repairs on the Arakawa Bay Bridge on the Metropolitan Expressway, which has been in service for about 50 years. With serious damage such as “peeling paint, corrosion of the foundation, and sections with missing material or fractures,” how will it be repaired?

Posted on August 12, 2026 by Editor in Chief

Overview of the Large-Scale Repair Work on the Arakawa Bay Bridge Since fiscal year 2014, the Metropolitan Expressway Authority has been carrying out large-scale renewal and repair work at various locations along 63.7 km of its 327.2 km total route as part of the “Metropolitan Expressway Renewal Project.” This magazine has also reported on large-scale renewal project sites such as the “Kousoku Daishi Bridge” and the “Higashi-Shinagawa Pier and Samezu Reclamation Area.” In the case of the Arakawa Bay Bridge, detailed inspections utilizing new technologies revealed approximately 4,500 instances of damage, 53% of which were attributed to corrosion and coating degradation; as a result, large-scale repair work was added to the project in 2024. Along with the “Haneda Tunnel” on Expressway No. 1, the renewal section is expected to span 21.6 km, with a projected project cost of 305.6 billion yen. Overview of the Arakawa Bay Bridge Opening Date: January 20, 1978

Length: Approximately 840 meters

Number of lanes: 8 lanes in both directions (6 lanes in both directions at the time of construction)

Structural Type: Truss bridge (central span is a steel-deck box-girder bridge)

Structural Overview: 4 fixed spans, 3 suspension spans; steel deck box girder in the central section. Functional enhancement and seismic retrofitting of the Arakawa Bay Bridge. 1987–1988: Repainting work

1995–1999: Widening project to expand the road to four lanes (Shin-Kiba to Kasai)

1995–1999: Seismic retrofitting of RC bridge piers

2001–2004: Installation of bridge collapse prevention systems

2008–2009: Seismic retrofitting of steel bridge piers

2008–2013: Seismic retrofitting of the superstructure; repainting of the truss floor system (damage occurred during construction due to the Great East Japan Earthquake)

2011–2012: Emergency Restoration Work Following the Great East Japan Earthquake The scope of this project covers a 460-meter section on the Koto Ward side, where work will include repainting the bridge, repairing various types of damage, and installing inspection walkways and permanent scaffolding. Although the main truss of the Arakawa Bay Bridge had been repainted once and the deck girders twice in the past, those projects involved “Type 3 surface preparation,” which removed only the degraded paint film, resulting in a thick coating. Since there is a risk that the coating could peel off if left as is, this time we will perform “Type 1 surface preparation”—which completely removes not only rust but also the old chlorinated rubber-based coating via metal blasting to expose the steel surface—and apply a fluorocarbon coating for a highly durable finish. In addition to the existing inspection walkways, two new walkways will be installed on the upper side of the truss section beneath the deck, and one on the lower side. Furthermore, permanent scaffolding will be installed in the central span. Other work includes replacing damaged drainage pipes, bolts, and gusset plates, as well as repairing areas of delamination on the reinforced concrete piers. Work will proceed from the Koto Ward side, with “temporary scaffolding erection,” “repair and reinforcement,” and “repainting” carried out one span at a time, gradually moving toward the Edogawa Ward side. The construction period is estimated to be approximately 8 months for scaffolding erection and related work, and another approximately 8 months for painting and inspection, for a total of about 7.5 years from March 29, 2025, to December 26, 2032. The Edogawa Ward side is scheduled to issue a contract in the future.

I visited the construction site where scaffolding has been set up and repair and painting work is about to begin. The area shown here is “Work Zone A,” located closest to Koto Ward, with scaffolding already in place. Repair and painting work will be carried out next. The steel structures to be painted and repaired number approximately 1,700 along the entire section (about 840 meters). The finished color will be a shade of blue named “Waterside Blue.”

read more

© Source travel watch

Uncategorized

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

Recent Posts

  • I Joined a Tour to Celebrate a 2-Year-Old Twin’s Birthday at the Popular Panda Spot, “Hong Kong Ocean Park”
  • [Naoki Wakabayashi’s Travel Photo Gallery] Tonle Sap Lake and Banteay Srei Temple (Cambodia)
  • Applications for the final ticket lottery for the Vermeer exhibition begin today. The Lake Biwa Hotel is currently offering packages that include admission tickets.
  • The Japan RV Association has certified 12 new RV camping facilities, including “RV Park Ezosumika Asahikawa,” where visitors can enjoy beautiful rural scenery and an on-site café.
  • “Peanuts Miniature Town,” a weekly series where you build the town where Snoopy and his friends live. The first issue comes with a doghouse and a Woodstock figurine.

Recent Comments

No comments to show.

Archives

  • September 2026
  • August 2026
  • July 2026
  • June 2026
  • May 2026
  • April 2026
  • March 2026
  • February 2026
  • January 2026
  • December 2025
  • November 2025
  • April 2024
  • March 2024
  • February 2024
  • January 2024
  • December 2023
  • November 2023
  • October 2023
  • September 2023
  • August 2023
  • July 2023
  • June 2023
  • May 2023
  • April 2023
  • March 2023
  • February 2023
  • January 2023
  • December 2022
  • November 2022
  • October 2022
  • September 2022
  • August 2022
  • July 2022
  • June 2022
  • May 2022
  • April 2022

Categories

  • Japan
  • JICA contributions
  • travelling
  • Uncategorized
©2026 Konrad News – The news site | Powered by Superb Themes
Go to mobile version